PROJECT PROFILE · LNG

Rovuma LNG

A planned onshore LNG development for Mozambique's Area 4

FEED / Pre-FID

Project Overview

Rovuma LNG is an onshore LNG development and export project for the Mamba resources in Area 4 of Mozambique’s Rovuma Basin, planned for the Afungi Peninsula near Palma. Mozambique Rovuma Venture (MRV) is advancing the project, with ExxonMobil leading the liquefaction facilities and Eni leading the upstream development.

Design and Schedule

The planned development comprises twelve modular, electrically driven liquefaction trains and associated facilities. Each train is designed for 1.5 million tonnes of LNG per year, for a total capacity of 18 million tonnes per year. The project is currently in FEED and has not yet reached final investment decision.

As of May 2026, the project remained pre-FID; a final investment decision in the third quarter of 2026 and first LNG in 2030 remained planning targets.

Participants and roles

Key participants and their project roles.

  • FEED contractor

    Design twelve modular, electrically driven liquefaction trains and associated facilities together with JGC.

    Scope
    Other
    Relationship start
    25 Sep 2024
  • United States

    ExxonMobil
    Operator

    Lead the liquefaction-facilities scope on behalf of MRV and award the FEED work to Technip Energies and JGC.

    Scope
    Onshore facilities
    Relationship start
    25 Sep 2024
  • Other

    Member of the SMDC consortium undertaking pre-FID engineering work for the first phase of Rovuma LNG.

    Scope
    Other