Project Overview
Greater PAJ is Angola’s first integrated cross-block development, combining Palas, Astraea and Juno in Block 31 with Urano and Dione in Block 31/21. The approximately US$5.1 billion project plans ten production wells and seven injection wells, targets around 252 million barrels of recoverable resources, and aims for first oil in the first half of 2029.
Equity Structure
| Block | Azule Energy | Sonangol E&P | SSI Thirty-One | Equinor |
|---|---|---|---|---|
| Block 31 | 26.67% (operator) | 45% | 15% | 13.33% |
| Block 31/21 | 50% (operator) | — | — | 50% |
FPSO and Subsea Execution
| Execution Area | Principal Party | Scope | Verified Milestone |
|---|---|---|---|
| Development and operation | Azule Energy | Cross-block development organization, operatorship and project operation | FID on 22 Jun 2026 |
| Full FPSO EPCIC | CIMC Raffles | Front-end engineering, design, procurement, construction, tow-out, installation and commissioning | Topside first steel cut in Jul 2026 |
| Offshore transport and installation | Saipem | Rigid pipelines, flexible facilities, umbilicals and subsea structures | Approximately US$1 billion over about 40 months |
| Subsea production system | Baker Hughes | Subsea production-system package | Confirmed in the FID contractor list |
| Umbilicals | OneSubsea | Project umbilical package | Confirmed in the FID contractor list |
| Flexible risers and flowlines | TechnipFMC | Supply of flexible risers and flowlines | Awarded on 22 Jun 2026 |
| Rigid pipe | Vallourec | Project rigid-pipe package | Confirmed in the FID contractor list |
Key Milestones
-
Final investment decision
The five-field cross-block development moved into full execution.
-
Topside construction begins
First steel was cut for the FPSO process modules.
-
Target first oil
The project is progressing toward the current official target.
Principal Sources
Azule Energy FID announcement; ANPG project announcement; CIMC Raffles EPCIC announcement; Saipem offshore award; Eni project-capacity announcement.
Participants and roles
Key participants and their project roles.
-
Azule Energy
An Angola-focused integrated energy company owned 50:50 by bp and Eni.
OperatorOperator with a 26.67% interest in Block 31 and a 50% interest in Block 31/21.
- Scope
- Ownership and governance