Eni Starts Coral North FLNG Drilling Campaign Offshore Mozambique
Eni and its Area 4 partners have started the Coral North drilling and completion campaign, covering up to six development wells. The 3.55-mtpa FLNG project is 72% complete and targets start-up in 2028.

Eni and its Area 4 partners in Mozambique’s Rovuma Basin have started the drilling and completion campaign for the Coral North FLNG project. The campaign moves the development beyond construction of the floating liquefaction unit and into field execution, while the start-up target remains 2028.
Operations began on 1 November and are expected to last about ten months. ENH–Saipem Drilling Company SA is carrying out the work with the deepwater drillship Saipem 12000 to support development of the northern part of the Coral reservoir in Rovuma Basin Area 4.
Mozambique’s National Petroleum Institute (INP) previously said the drilling and completion campaign would run for about 270 days and cover up to six development wells, with four in the first phase and two in the second. The wells will supply feed gas to Coral North FLNG.
ENH–Saipem Drilling Company brings together participation from Mozambique’s national oil company ENH and Saipem interests. Eni described the campaign as the first time a company with Mozambican participation has assumed a direct operational role in the country’s offshore drilling, extending local participation into one of the development’s more technically and capital-intensive activities.
Coral North is the second FLNG development in Area 4 after Coral South. The partners are Eni, China National Petroleum Corporation, ENH, KOGAS and XRG. Mozambique’s government approved the development plan in April 2025, and the partners announced the final investment decision in October of that year.
Coral North FLNG is designed to produce 3.55 mtpa of LNG from six subsea wells. The unit is based on the Coral South FLNG design and is under construction at Samsung Heavy Industries in South Korea. Its hull was launched in January 2026, and INP said in late October that overall project progress had reached 72%.
Coral South FLNG entered production in late 2022 as the first development to produce gas from the Rovuma Basin. Eni says the addition of Coral North will lift Mozambique’s combined LNG output from the two projects to about 7 mtpa.
The start of drilling does not mean that the FLNG unit itself is complete. Coral North is now advancing through offshore well construction and floating-facility fabrication in parallel. Drilling and completion, subsea connections, unit integration, tow-out, installation and commissioning must still be completed before the project can reach its 2028 start-up target.