PROJECT PROFILE

Agogo Integrated West Hub

The Agogo FPSO reached 80,150 bpd while maintaining zero routine flaring.

In production

Project overview

The Agogo Integrated West Hub develops the Agogo and Ndungu fields in Block 15/06 through the Agogo FPSO and the existing N’Goma FPSO. First oil was achieved in July 2025. Following early-well tie-ins and production optimisation, the Agogo FPSO reached 80,150 bpd in October 2026, its highest rate since first oil.

Latest development and boundaries

The 80,150 bpd rate is approximately 66.8% of the FPSO’s 120,000 bpd design capacity. Zero routine flaring means associated gas is not continuously flared as the normal production solution; it does not exclude safety or non-routine flaring. In October 2026, the Agogo FPSO asset company also priced US$1.458 billion of project bonds for refinancing and related purposes.

Sources

Azule Energy official disclosure; Yinson Production official disclosure;