PROJECT PROFILE

North Field East (NFE)

Qatar’s North Field East expansion links offshore gas supply with large-scale LNG liquefaction, storage and loading at Ras Laffan.

Construction and start-up preparation

Project overview

North Field East (NFE) is the eastern phase of Qatar’s North Field expansion, developed by QatarEnergy with project execution by QatarEnergy LNG. Four large LNG trains are supported by offshore wellhead facilities, pipelines and cables, onshore utilities, and storage and loading infrastructure. NFE and North Field West (NFW) are separate phases within the wider expansion programme.

The four trains each have a nominal capacity of 8 mtpa. The developer describes the overall incremental capacity as approximately 33 mtpa, taking Qatar from 77 to 110 mtpa. These figures describe nominal train capacity and the overall expansion increment; they are planned capacities.

Gas supply, liquefaction and export infrastructure

McDermott coordinates the offshore scope. QFAB fabricates four wellhead topsides and subsea infrastructure, supported by the Batam yard. The approximately 300 miles of pipelines and 140 miles of 33kV cables disclosed by McDermott belong to the wider NFE/NFS contract combination.

Contract structure

Tier 1 comprises owner/operator awards and their consortium members. Tier 2 comprises major subcontractors and suppliers appointed directly by Tier 1 contractors.

Tier 1 | Direct contracts

Direct client / awarding party Contractor / consortium member Scope
QatarEnergy (formerly Qatar Petroleum) Technip Energies CTJV with Chiyoda delivers four LNG trains, utilities and carbon-capture facilities.
QatarEnergy (formerly Qatar Petroleum) Chiyoda Corporation CTJV partner with Technip Energies for the onshore LNG facilities.
QatarEnergy (formerly Qatar Petroleum) McDermott International, Ltd. Eight NFE wellhead topsides and associated pipelines and cables; the wider contract also covers NFS scopes.
QatarEnergy (formerly Qatar Petroleum) Samsung C&T Corporation Three 187,000 m³ LNG storage tanks, three loading facilities and transfer pipelines.
QatarEnergy (formerly Qatar Petroleum) Técnicas Reunidas, S.A. Direct Qatar Petroleum EPC-3 award for associated facilities, including product storage and loading, MEG facilities, pipelines and CO₂ transport and wellhead injection facilities.
QatarEnergy (formerly Qatar Petroleum) Baker Hughes Twelve gas turbines and 24 centrifugal compressors for four LNG trains.

Tier 2 | Major subcontracts

Direct client / awarding party Contractor / consortium member Scope
McDermott Qatar Fabrication Company W.L.L. Fabrication and loadout subcontract from McDermott, including four wellhead topsides and subsea infrastructure.

Related developments

North Field West (NFW) | Al Shaheen Ruya

Sources

Baker Hughes: NFE equipment; Technip Energies: NFE EPCC; McDermott: direct NFE EPCI award; McDermott: North Field expansion; QFAB: NFE fabrication contract; Samsung C&T: LNG storage and loading; Técnicas Reunidas: associated facilities;