Company overview
BOMESC began operations in 1996 and was reorganised as BOMESC Offshore Engineering Company Limited in 2012. Headquartered in Tianjin Binhai New Area, it listed on the Shanghai Stock Exchange in 2016 under stock code 603727.
Its Lingang yard covers about 760,000 m² and has 700 metres of owned deepwater quay plus 325 metres of undeveloped deepwater quay resources. BOMESC focuses on customised module design, procurement, fabrication, commissioning and loadout, with an expanding capability in FPSO integration.
Core capabilities
FPSO topsides modulesLNG and gas modulesFixed-facility accommodationFPSO integration and commissioningMining and onshore modulesDigital fabrication
Recent representative projects
| Project / asset | Client or development | Role | Disclosed relationship and status |
|---|---|---|---|
| NFPS COMP5 | QatarEnergy LNG / Saipem and COOEC | Accommodation module engineering, procurement and fabrication | Tianjin BOMESC signed a roughly US$220 million contract with Saipem Offshore Construction in April 2026, running through March 2030. |
| Hammerhead FPSO | ExxonMobil Guyana / MODEC | Topsides modules, chemical skids, electrical rooms and SRU water-treatment modules | Four contracts with OFS, ABB and VWS total about US$190–240 million, with staged completion through June 2027. |
| GranMorgu FPSO | TotalEnergies Block 58 / SBM Offshore and Technip Energies | Detailed and fabrication engineering, procurement and fabrication for nine modules | Contract signed with STS VOF in January 2025; first steel was cut on 20 May 2025 and completion is planned for January 2027. |
| Raia FPSO | Equinor / MODEC | Seventeen topsides modules | Module contract signed in October 2023 and fabrication started at Tianjin Lingang in February 2024. |
| Uaru / FPSO Errea Wittu | ExxonMobil Guyana / MODEC | More than one third of the vessel's topsides modules | All BOMESC products were delivered in 2025; the FPSO arrived in Guyana in August 2026 for offshore preparation and commissioning. |
| Bacalhau FPSO | Equinor / MODEC | Water treatment, chemical injection and workshop/laboratory modules | The final three modules were delivered in September 2023. Bacalhau achieved first oil in October 2025. |
| Mero 2 / FPSO Sepetiba | SBM Offshore / Petrobras Mero | Topsides, hull integration, assembly and commissioning | Sailed from the Lingang yard in June 2023 and entered hire in January 2024, demonstrating full-yard FPSO integration capability. |