PROJECT PROFILE · FPSO

Búzios

A 12-FPSO phased pre-salt development in Brazil's Santos Basin

Producing / Expansion

Project Overview

Búzios is a major ultra-deepwater pre-salt field in Brazil’s Santos Basin, approximately 180 kilometres off the coast of Rio de Janeiro state, with Petrobras as operator. Interests in the shared Búzios/Tambuatá reservoir are Petrobras 88.99%, CNOOC Petroleum Brasil 7.34% and CNODC Brasil 3.67%.

The development comprises 12 planned FPSO systems. P-74 through P-77, Almirante Barroso, P-78, Almirante Tamandaré and P-79 are in production. P-80, P-82 and P-83 are under construction for planned installation in 2027, while Búzios 12 (P-91) is being tendered under a BOT model. The field reached average oil production of 1.2 million barrels per day on 26 June 2026.

FPSO Development and Engineering Scope

Code FPSO Milestone Contractor / operator Engineering scope Subsea scope
Búzios 1 P-74 First oil: Apr 2018
In production
Petrobras
Owned and operated
Toyo Engineering / EBR
Topsides engineering, procurement, fabrication, commissioning and integration in Brazil
Legacy subsea production system
Búzios 2 P-75 First oil: Nov 2018
In production
Petrobras
Owned and operated
QGI Brasil
Module fabrication, hull integration and completion
Legacy subsea production system
Búzios 3 P-76 First oil: Feb 2019
In production
Petrobras
Owned and operated
Techint E&C
Engineering, procurement, module fabrication, integration and commissioning support
Legacy subsea production system
Búzios 4 P-77 First oil: Mar 2019
In production
Petrobras
Owned and operated
QGI Brasil
Module fabrication, hull integration and completion
Legacy subsea production system
Búzios 5 Almirante Barroso MV32 First oil: May 2023
In production
MODEC
EPCI, 21-year charter and O&M
MODEC
VLCC conversion and overall FPSO delivery
SOFEC: spread mooring
Saipem
EPCI for steel catenary risers, flowlines, service lines and export pipeline
Búzios 6 P-78 First oil: Dec 2025
Production ramp-up
Seatrium
Full-scope EPCC
HD Hyundai Heavy Industries: hull blocks and living quarters
Seatrium: multi-country module fabrication and final integration in Singapore
TechnipFMC
EPCI for rigid and flexible pipe, umbilicals, terminations and mooring
Búzios 7 Almirante Tamandaré First oil: Feb 2025
In production
SBM Offshore
26.25-year lease and operations
SBM Offshore: Fast4Ward solution
China Merchants Industry: MPF B newbuild hull
Saipem
SURF EPCI for rigid risers, flowlines and associated systems
Búzios 8 P-79 First oil: May 2026
Production ramp-up
Saipem / Hanwha Ocean
Joint EPC
Hanwha Ocean: hull and final integration and commissioning at Geoje
Saipem: topsides, mooring, hook-up and start-up
Subsea7
Subsea EPCI for rigid risers and flowlines
Búzios 9 P-80 Under construction
Installation planned for 2027
Seatrium
FPSO EPC
CIMC Raffles: newbuild hull and living quarters
Seatrium: multi-country module fabrication and final integration in Singapore
Subsea7
EPCI for approximately 102 km of rigid risers and flowlines
Búzios 10 P-82 Under construction
Installation planned for 2027
Seatrium
FPSO EPC
Seatrium
Engineering, procurement and construction of the newbuild FPSO
Allseas
EPCI for rigid risers, flowlines and subsea structures connecting 16 wells
Búzios 11 P-83 Under construction
Installation planned for 2027
Seatrium
FPSO EPC
CIMC Raffles: newbuild hull and living quarters
Seatrium: multi-country module fabrication and final integration in Singapore
Subsea7
Subsea interconnection EPCI for 15 wells
Búzios 12 P-91 BOT tender in progress
Start-up planned after 2031
Petrobras
Future owner and operator
BOT scope covers design, construction, assembly, initial operations and transfer Planned connection of 16 wells and field-wide gas-export hub function

Participants and roles

Key participants and their project roles.

  • Brazil

    Petrobras
    Operator

    Operator of the Búzios field and principal developer of its phased FPSO production systems.

    Scope
    Ownership and governance
    Relationship start
    2010
  • Integration assembler

    Full-scope EPCC for P-78 and EPC delivery of P-80, P-82 and P-83.

    Scope
    Offshore facilities and operations
    Relationship start
    10 May 2021
  • Hull builder

    Construction of the newbuild hulls and living quarters for P-80 and P-83.

    Scope
    Offshore facilities and operations
    Relationship start
    2022
  • Netherlands

    SBM Offshore
    Shipowner / lessor

    Design, construction and installation of FPSO Almirante Tamandaré, followed by a 26.25-year lease and operations contract.

    Scope
    Offshore facilities and operations
    Relationship start
    25 Feb 2021
  • EPC contractor

    Joint EPC delivery of P-79 with Hanwha Ocean, plus subsea EPCI for Búzios 5 and Búzios 7.

    Scope
    Offshore facilities and operations
    Relationship start
    6 Jul 2020
  • Japan

    MODEC
    Shipowner / lessor

    EPCI delivery of FPSO Almirante Barroso MV32, followed by a 21-year charter and operations and maintenance services.

    Scope
    Offshore facilities and operations
  • 英国

    TechnipFMC plc
    EPCI contractor

    Subsea EPCI for Búzios 6, including rigid and flexible pipe, umbilicals, terminations and the FPSO mooring system.

    Scope
    Subsea systems
    Relationship start
    16 Nov 2021
  • 韩国

    Hanwha Ocean
    EPC contractor

    Joint EPC delivery of P-79 with Saipem, including hull construction and final integration and commissioning at Geoje.

    Scope
    Offshore facilities and operations
    Relationship start
    11 Jun 2021
  • 英国/卢森堡

    Subsea7
    EPCI contractor

    Subsea EPCI for Búzios 8, Búzios 9 and Búzios 11.

    Scope
    Subsea systems
    Relationship start
    11 May 2022
  • 瑞士

    Allseas
    EPCI contractor

    Full subsea EPCI for Búzios 10, including rigid risers, flowlines and associated structures.

    Scope
    Subsea systems
    Relationship start
    19 Sep 2024
  • Brazil

    QGI Brasil S.A.
    Integration assembler

    Module fabrication, hull integration and completion work for P-75 and P-77.

    Scope
    Offshore facilities and operations
  • 意大利/阿根廷

    Techint Engineering & Construction
    Integration assembler

    Engineering, procurement, module fabrication, hull integration and commissioning support for P-76.

    Scope
    Offshore facilities and operations
  • Japan

    Toyo Engineering Corporation
    Topsides builder

    Joint delivery of P-74 topsides engineering, procurement, fabrication, commissioning and start-up support.

    Scope
    Offshore facilities and operations
  • Brazil

    EBR Estaleiros do Brasil Ltda.
    Integration assembler

    Brazilian module fabrication and hull-integration scope for P-74.

    Scope
    Offshore facilities and operations
  • 韩国

    HD Hyundai Heavy Industries
    Hull builder

    Construction of P-78 hull blocks and living quarters.

    Scope
    Offshore facilities and operations
  • China

    China Merchants Industry
    Hull builder

    Construction of the Fast4Ward MPF B newbuild hull for FPSO Almirante Tamandaré.

    Scope
    Offshore facilities and operations