COMPANY PROFILE · ENERGY ENGINEERING

Technip Energies

Engineering and technology for LNG, offshore facilities and decarbonization infrastructure

Company Overview

Technip Energies became an independent company in 2021 and is headquartered in Nanterre, France. It is a global engineering and technology company serving energy infrastructure and decarbonization markets. Its two business segments, Project Delivery and Technology, Products and Services, span LNG, hydrogen, ethylene, sustainable chemistry, offshore production facilities and CO₂ management.

According to the company’s 2025 reporting, Technip Energies has more than 18,000 employees across 35 countries, generated €7.2 billion of revenue in 2025 and is listed on Euronext Paris.

Business Model and Core Capabilities

Consulting & FEEDEPC / EPCC / EPCIOnshore LNG & ModularizationFLNG & FPSO TopsidesElectrified ProcessesIntegrated CCUS

Technip Energies can support projects from concept studies, FEED and process technology through procurement, construction, installation, commissioning and start-up. Its role varies by contract: GranMorgu focuses on FPSO topsides engineering and modularization; Commonwealth LNG uses the SnapLNG by T.EN modular solution; Coral Norte is under FLNG EPCIC; the Qatar North Field projects, Ruwais LNG and Marsa LNG demonstrate large-scale lower-carbon LNG delivery; and Net Zero Teesside Power integrates low-carbon power generation with carbon capture.

Technip Energies and TechnipFMC are separate companies. This page does not include TechnipFMC’s subsea production-system or subsea EPCI business.

Representative Project Portfolio

Project Type / Status Technip Energies Role Principal Scope Scale or Milestone
GranMorgu Suriname / FPSO in execution Joint FPSO contractor Topsides engineering, design, modularization and fabrication oversight Major award in 2024
Commonwealth LNG United States / LNG in full execution EPC contractor Six modular SnapLNG trains and associated facilities 9.5 Mtpa; full notice to proceed in 2026
Coral Norte FLNG Mozambique / FLNG in execution EPCIC consortium member Enhanced-replica delivery with JGC and Samsung Heavy Industries Approximately 3.6 Mtpa; main award in 2026
Rovuma LNG Mozambique / Pre-FID FEED contractor Design with JGC for 12 modular electric-drive liquefaction trains Planned 18 Mtpa; no subsequent EPC share inferred
Qatar North Field East Qatar / EPCC in execution CTJV contractor Four large LNG trains, utilities and carbon capture facilities 4 × 8 Mtpa; awarded in 2021
Qatar North Field South Qatar / EPCC in execution Joint-venture lead Two large LNG trains and carbon capture and storage facilities 2 × 8 Mtpa; awarded in 2023
Qatar North Field West Qatar / EPCC in execution Joint-venture lead Two enhanced-replica trains and associated carbon capture and storage 2 × 8 Mtpa; awarded in 2026
Ruwais LNG United Arab Emirates / EPC in execution Joint-venture lead Two electric-drive liquefaction trains and associated facilities 9.6 Mtpa; awarded in 2024
Marsa LNG Oman / EPC in execution EPC contractor Electric-drive liquefaction train and associated facilities 1 Mtpa; site works started in 2025
Net Zero Teesside Power United Kingdom / EPC in execution Consortium lead Combined-cycle power, carbon capture and compression facilities Up to 742 MW; up to 2 Mtpa of CO₂ capture

Related projects and roles

  • Oil and gas development · Suriname

    GranMorgu

    Suriname's first large-scale offshore oil and gas development, centered on a newbuild FPSO.

    EPCI contractor

    Joint FPSO construction and installation with SBM Offshore, focusing on topsides engineering, design, modularization and fabrication oversight.

    Scope
    Offshore facilities and operations
    Relationship start
    14 Nov 2024
  • LNG facility · United States

    Commonwealth LNG

    A planned 9.5 million-tonne-per-year LNG export facility in Louisiana, United States.

    EPC contractor

    EPC delivery of a 9.5 Mtpa LNG export facility with six modular trains using the SnapLNG by T.EN solution.

    Scope
    Onshore facilities
    Relationship start
    15 May 2026
  • LNG facility · Mozambique

    Coral Norte FLNG

    A newbuild FLNG development in Area 4 of Mozambique's Rovuma Basin.

    EPCIC contractor

    EPCIC delivery of the approximately 3.6 Mtpa Coral Norte FLNG with JGC and Samsung Heavy Industries.

    Scope
    Offshore facilities and operations
    Relationship start
    8 Jun 2026
  • LNG facility · Mozambique

    Rovuma LNG

    A planned 18 million-tonne-per-year onshore LNG development in Mozambique's Area 4.

    FEED contractor

    FEED with JGC for 12 modular electric-drive liquefaction trains; no subsequent EPC share is inferred.

    Scope
    Onshore facilities
    Relationship start
    25 Sep 2024
  • LNG facility · Qatar

    Qatar North Field East
    EPC contractor

    Joint-venture EPCC with Chiyoda for four large LNG trains, utilities and carbon capture facilities.

    Scope
    Onshore facilities
    Relationship start
    9 Feb 2021
  • LNG facility · Qatar

    Qatar North Field South
    EPC contractor

    Joint-venture lead with CCC for EPCC of two large LNG trains and carbon capture and storage facilities.

    Scope
    Onshore facilities
    Relationship start
    16 May 2023
  • LNG facility · Qatar

    Qatar North Field West
    EPC contractor

    Joint-venture lead with CCC and GAC for EPCC of two large LNG trains and associated carbon capture and storage.

    Scope
    Onshore facilities
    Relationship start
    25 Feb 2026
  • LNG facility · United Arab Emirates

    Ruwais LNG
    EPC contractor

    Joint-venture lead with JGC and NMDC Energy for EPC of two electric-drive liquefaction trains and associated facilities.

    Scope
    Onshore facilities
    Relationship start
    12 Jun 2024
  • LNG facility · Oman

    Marsa LNG
    EPC contractor

    EPC delivery of a 1 Mtpa electric-drive liquefaction train and associated facilities.

    Scope
    Onshore facilities
    Relationship start
    22 Apr 2024
  • United Kingdom

    Net Zero Teesside Power
    EPC contractor

    Consortium lead for integrated combined-cycle power, carbon capture and compression under the full onshore EPC package.

    Scope
    Onshore facilities
    Relationship start
    10 Dec 2024