Project Overview
Payara is the third offshore development in the Stabroek Block and is operated by ExxonMobil Guyana Limited. Stabroek interests are ExxonMobil Guyana 45%, Hess Guyana 30% and CNOOC Petroleum Guyana 25%. The development achieved first oil through the Prosperity FPSO on 14 November 2023.
FPSO and Local Execution
Prosperity uses the newbuild Fast4Ward MPF 3 hull and has design oil-processing capacity of 220,000 barrels per day and storage of approximately 2 million barrels. Shanghai Waigaoqiao Shipbuilding built the hull, Dyna-Mac fabricated the main topsides modules, and Keppel fabricated riser and mooring structures and integrated the modules. Saipem completed subsea EPCI and fabricated 48 rigid jumpers in Georgetown. ExxonMobil Guyana acquired the FPSO in November 2024, and SBM Offshore continues O&M through 2033.
Key Milestones
-
Government approval
Payara moves into full execution.
-
FPSO award
SBM Offshore receives construction, installation and initial lease-and-operate scope.
-
First oil
Prosperity starts production.
-
FPSO purchase completed
ExxonMobil Guyana takes ownership while SBM Offshore continues O&M.
FPSO Construction and Execution Scope
| Workstream | Executing Party | Scope | Status |
|---|---|---|---|
| Overall FPSO delivery | SBM Offshore | Engineering, construction, installation and initial lease operations | Completed |
| Hull construction | Shanghai Waigaoqiao Shipbuilding | Fast4Ward MPF 3 hull | Completed |
| Modules and integration | Seatrium (legacy Keppel O&M) | Riser and mooring structures and topsides integration | Completed |
| Subsea works | Saipem | Subsea EPCI and local jumper fabrication in Guyana | Completed |
| Operations and maintenance | SBM Offshore | Continued O&M after the FPSO sale through 2033 | Ongoing |
Portfolio Navigation
Participants and roles
Key participants and their project roles.
-
Operator
Operator of Payara and owner of FPSO Prosperity.
- Scope
- Ownership and governance
-
EPCI contractor
Engineering, procurement, construction and installation of FPSO Prosperity, followed by initial lease-and-operate services.
- Scope
- Offshore facilities and operations
Shipowner / lessorOperations and maintenance of FPSO Prosperity under the integrated model through 2033.
- Scope
- Offshore facilities and operations
- Relationship start
- 2 May 2023
-
Shanghai Waigaoqiao Shipbuilding Co., Ltd.Hull builder
Construction of the Fast4Ward multi-purpose floater hull for FPSO Prosperity.
- Scope
- Offshore facilities and operations
-
Integration assembler
Topsides integration and completion of FPSO Prosperity at the Singapore yard.
- Scope
- Offshore facilities and operations
-
EPCI contractor
Subsea umbilicals, risers and flowlines engineering, procurement, construction and installation for Payara.
- Scope
- Subsea systems
- Relationship start
- 14 Nov 2019