Project Overview
Yellowtail is the fourth offshore development in the Stabroek Block and is operated by ExxonMobil Guyana Limited. Stabroek interests are ExxonMobil Guyana 45%, Hess Guyana 30% and CNOOC Petroleum Guyana 25%. The development achieved first oil through the ONE GUYANA FPSO on 8 August 2025.
FPSO Construction and Current Operations
ONE GUYANA uses the newbuild Fast4Ward MPF 3 hull and has design oil-processing capacity of 250,000 barrels per day and storage of approximately 2 million barrels. Shanghai Waigaoqiao Shipbuilding built the hull; SBM Offshore and McDermott jointly executed the EPC phase through a special-purpose company; QMW fabricated three topsides modules in Qingdao; and Seatrium completed module fabrication, installation, integration and commissioning support. SBM Offshore led installation and initial lease operations. ExxonMobil Guyana acquired the FPSO ahead of schedule in February 2026, while SBM Offshore continues operations and maintenance through 2035.
Key Milestones
-
FPSO award
SBM Offshore receives construction, installation and initial lease-and-operate scope.
-
Construction completed and sailaway
Hull, topsides and integration work are completed before the FPSO departs Singapore for Guyana.
-
First oil
The development starts production ahead of its original schedule.
-
FPSO purchase completed
ExxonMobil Guyana takes ownership while SBM Offshore continues O&M through 2035.
FPSO Construction and Execution Scope
| Workstream | Executing Party | Scope | Status |
|---|---|---|---|
| Overall FPSO delivery | SBM Offshore | Construction, installation and initial lease operations | Completed |
| Joint EPC execution | McDermott | Project management, basic design, procurement, engineering, integration and commissioning | Completed |
| Hull construction | Shanghai Waigaoqiao Shipbuilding | Fast4Ward MPF 3 hull | Completed |
| Topsides modules | QMW | Fabrication of three topsides modules in Qingdao | Completed |
| Modules and integration | Seatrium | Module fabrication, installation, integration and commissioning support | Completed |
| Operations and maintenance | SBM Offshore | Continued O&M after the FPSO sale through 2035 | Ongoing |
Portfolio Navigation
Participants and roles
Key participants and their project roles.
-
Operator
Project operator and owner of the ONE GUYANA FPSO.
- Scope
- Ownership and governance
- Relationship start
- 5 Apr 2022
-
EPCI contractor
Construction and installation of the ONE GUYANA FPSO, together with up to two years of initial lease and operations services.
- Scope
- Offshore facilities and operations
- Relationship start
- 5 Apr 2022
Shipowner / lessorContinued operations and maintenance under an integrated model after the FPSO sale, extending to 2035.
- Scope
- Offshore facilities and operations
- Relationship start
- 8 Aug 2025
-
Shanghai Waigaoqiao Shipbuilding Co., Ltd.Hull builder
Construction and delivery of the Fast4Ward MPF 3 hull used for FPSO ONE GUYANA.
- Scope
- Offshore facilities and operations
- Relationship start
- 2020
-
McDermott International, Ltd.EPC contractor
Joint EPC execution with SBM Offshore, including project management, basic design, procurement, engineering, integration and commissioning.
- Scope
- Offshore facilities and operations
- Relationship start
- 18 Nov 2021
-
Qingdao McDermott Wuchuan Offshore Engineering Company Ltd.Topsides builder
Fabrication of three ONE GUYANA topsides modules at the QMW yard in Qingdao.
- Scope
- Offshore facilities and operations
- Relationship start
- 2022
-
Integration assembler
Topsides fabrication, installation and integration, with pre-commissioning and commissioning support in Singapore.
- Scope
- Offshore facilities and operations
- Relationship start
- 2022