Project Overview
Whiptail is the sixth offshore development in the Stabroek Block and is operated by ExxonMobil Guyana Limited. Stabroek interests are ExxonMobil Guyana 45%, Hess Guyana 30% and CNOOC Petroleum Guyana 25%. The project will be developed through FPSO Jaguar and is targeting first oil in 2027.
FPSO and Delivery Model
FPSO Jaguar uses SBM Offshore’s seventh newbuild Fast4Ward MPF concept; the MPF 5 hull assigned to the project was built by Shanghai Waigaoqiao Shipbuilding. The FPSO has design oil-processing capacity of 250,000 barrels per day and storage of approximately 2 million barrels. SBM Offshore is building and installing the unit under a Sale & Operate model, with ownership transferring to ExxonMobil Guyana before installation. Seatrium is fabricating modules and completing integration. SBM Offshore is expected to operate and maintain the FPSO for approximately ten years after start-up.
Key Milestones
-
FID and FPSO award
Whiptail moves into full execution and SBM Offshore receives the FPSO Jaguar construction and installation contract.
-
Modules and integration award
Seatrium receives topsides and overall integration scope.
-
Module lifting and integration
The project continues to advance on schedule.
-
Target first oil
The current planned start-up milestone.
FPSO Construction and Execution Scope
| Workstream | Executing Party | Scope | Status |
|---|---|---|---|
| Overall FPSO delivery | SBM Offshore | Construction and installation of FPSO Jaguar under the Sale & Operate model | In progress |
| Hull construction | Shanghai Waigaoqiao Shipbuilding | Fast4Ward MPF 5 hull | Completed |
| Modules and integration | Seatrium | Topsides modules, associated structures and integration | In progress |
| Operations and maintenance | SBM Offshore | Planned O&M for approximately ten years after start-up | Pre-start-up |
Portfolio Navigation
Participants and roles
Key participants and their project roles.
-
Operator
Project operator and future owner of the Jaguar FPSO.
- Scope
- Ownership and governance
- Relationship start
- 12 Apr 2024
-
EPCI contractor
Construction and installation of the Jaguar FPSO under the Sale and Operate model.
- Scope
- Offshore facilities and operations
- Relationship start
- 12 Apr 2024
Shipowner / lessorPlanned operation of the FPSO for approximately 10 years after start-up under the operations and maintenance framework.
- Scope
- Offshore facilities and operations
- Relationship start
- 12 Apr 2024
-
Integration assembler
Topsides fabrication and overall integration work for the Jaguar FPSO.
- Scope
- Offshore facilities and operations
- Relationship start
- 16 May 2024
-
Shanghai Waigaoqiao Shipbuilding Co., Ltd.Hull builder
Construction and delivery of the Fast4Ward MPF 5 hull used for FPSO Jaguar.
- Scope
- Offshore facilities and operations
- Relationship start
- 2022